Construction update

Construction Update is published periodically and provides information about the progress of major building and renovation projects. Information is provided to the Record by facilities management.

Danforth Campus

Brauer Hall

The building will be a LEED gold rating. Monthly LEED meetings will be held.

Busch Hall renovation

Work continues on electrical rough-ins, plumbing, fire protection and the HVAC.

South 40 Umrath House replacement

The reconciliation of the project scope and budget has been concluded. The trench drain was completed in late November. Workers will start building panels in mid-December.

South 40 utilities

The contractor has completed the excavation of the chiller site and is cutting in footings. The north- and west-side footing excavation was completed in November. Final plans for the chiller plant were issued in November for bid to subcontractors. New boilers are in operation to provide heat to the South 40 residence halls.

Wohl Center replacement

The reconciliation of the project scope and budget has been concluded. Concrete work continues. The LEED team is working to achieve a target silver LEED rating.